After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD. This is an example of____________. A. Qualitative risk analysis B. Risk Appetite C. Quantitative risk analysis D. Risk Tolerance Suggested Answer: C This question is in 712-50 EC-Council Certified CISO (CCISO) Exam For getting EC-Council Certified CISO (CCISO) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by EC-Council. Trademarks, certification & product names are used for reference only and belong to EC-Council. The website does not contain actual questions and answers from EC-Council's Certification Exam.