After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

QuestionsCategory: PMPAfter reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
Admin Staff asked 1 year ago
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months.
Based on the new timeline, what should the project manager do?

A. Plan for overtime, apply crashing and fast tracking, and share the risk of failure with project stakeholders

B. Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that ts the expected timeline

C. Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D. Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline B










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.