All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day. What should the project manager do to prevent these delays? A. Meet with the team in 2 weeks to respond to all of the open tasks. B. Review the Pareto diagram to identify the source of delays. C. Delegate the decision-making authority of some tasks to the team. D. Consolidate the decision-making authority to remain with the project manager. Correct Answer: C This question is in PMP exam For getting PMP Certificate