All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day. What should the project manager do to prevent these delays?

QuestionsCategory: PMPAll project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day. What should the project manager do to prevent these delays?
Admin Staff asked 1 year ago
All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day.
What should the project manager do to prevent these delays?

A. Meet with the team in 2 weeks to respond to all of the open tasks.

B. Review the Pareto diagram to identify the source of delays.

C. Delegate the decision-making authority of some tasks to the team.

D. Consolidate the decision-making authority to remain with the project manager.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.