An agile project is running its fth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work. What should the project manager do? A. Ask the team to have a lower commitment for the next iteration. B. Implement a checkpoint in the iteration to verify if the team is on track. C. Ask for additional team members to maintain the velocity. D. Conduct a focused retrospective to help the team to discover the root cause. Correct Answer: D This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer