An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel con dent about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now. What should the project manager do to mitigate this risk?

QuestionsCategory: PMPAn agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel con dent about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now. What should the project manager do to mitigate this risk?
Admin Staff asked 1 year ago
An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel con dent about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.
What should the project manager do to mitigate this risk?

A. Extend the sprint end date in anticipation of feedback from the product owner that will require extra work.

B. Schedule an additional interim demo with the product owner.

C. Address the issue as part of the retrospective.

D. Ask the team to work overtime toward the end of the sprint to meet the original sprint end date.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.