An engineer must implement a disaster recovery policy for the Cisco UCS infrastructure. The solution must meet these criteria: ✑ The Recovery Point Objective must be 48 hours. ✑ The backup must use encrypted transmission. The Recovery Time Objective must be 4 hours. Which configuration set must be used in the scheduled backup to meet these requirements? A. Protocol: FTP Schedule: Bi-Weekly B. Protocol: SFTP Schedule: Weekly C. Protocol: TFTP Schedule: Bi-Weekly D. Protocol: SCP Schedule: Daily Suggested Answer: D Reference: https://pediaa.com/what-is-the-difference-between-scp-and-sftp/#:~:text=based%20on%20SSH.-,The%20main%20difference%20between%20SCP% 20and%20SFTP%20is%20that%20SCP,which%20is%20faster%20than%20SCP This question is in 350-601 DCCOR exam For getting CCNP Data Center Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Cisco. Trademarks, certification & product names are used for reference only and belong to Cisco.