An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client’s project manager has no agile experience. How should the project manager ensure that the client is effectively represented in the daily meetings?

QuestionsCategory: PMPAn equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client’s project manager has no agile experience. How should the project manager ensure that the client is effectively represented in the daily meetings?
Admin Staff asked 1 year ago
An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.
How should the project manager ensure that the client is effectively represented in the daily meetings?

A. Recommend agile training programs that best suit the client project manager's schedule.

B. Propose a session for essential agile knowledge transfer for the client team to align with the daily meeting goals.

C. Realign the project to a predictive approach to ensure optimal collaboration between the teams.

D. Provide the client project manager with agile best practice documents and web resources.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.