An internal audit report reveals that a legacy system is no longer supported. Which of the following is the risk practitioner’s MOST important action before recommending a risk response? A. Explore the feasibility of replacing the legacy system. B. Identify other legacy systems within the organization. C. Assess the potential impact and cost of mitigation. D. Review historical application downtime and frequency. Suggested Answer: C This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.