An IS auditor is evaluating the progress of a web-based customer service application development project. Which of the following would be MOST helpful for this evaluation? A. Developer status reports B. Critical path analysis reports C. Change management logs D. Backlog consumption reports Suggested Answer: B Community Answer: B This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.