An IS auditor noted that a change to a critical calculation was placed into the production environment without being tested. Which of the following is the BEST way to obtain assurance that the calculation functions correctly? A. Check regular execution of the calculation batch job. B. Interview the lead system developer. C. Obtain post-change approval from management. D. Perform substantive testing using computer-assisted audit techniques (CAATs). Â Suggested Answer: D Community Answer: D This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.
Please login or Register to submit your answer