An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project. What should the project lead do? A. Ask that estimations be provided only by senior developers. B. Recommend a different estimation method in the retrospective. C. Allocate more time for estimation in the sprint planning. D. Review and update the estimations in the daily standup. Correct Answer: B This question is in PMP exam For getting PMP Certificate