An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed. What should the project lead recommend?

QuestionsCategory: PMPAn organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed. What should the project lead recommend?
Admin Staff asked 1 year ago
An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.
What should the project lead recommend?

A. Send weekly reports to the PMO, and use a kanban board for the product owner and the project team

B. Send the weekly report to the PMO and the product owner, and use a kanban board for the project team

C. Invite the PMO manager to the daily standup with the project team and product owner

D. Send weekly reports to all stakeholders, including the project team and the product owner A










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.