An organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief. What should the project lead do?

QuestionsCategory: PMPAn organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief. What should the project lead do?
Admin Staff asked 1 year ago
An organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief.
What should the project lead do?

A. Ask the solutions architect to contact the legal department and create the epic(s) in the product backlog.

B. Advise the SME that there are no legal requirements identified in the project brief and continue the workshop.

C. Ask the project sponsor to contact the legal department and identify the legal impact.

D. Add the legal department to the list of stakeholders and contact them to discuss the project scope.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.