As part of project execution, a contractor proposed and conducted site acceptance tests and pre-implementation technical training. However, during the implementation phase, the project manager notes a clear gap in the project team’s competence in following the implementation of the technical requirements. What should the project manager have done to avoid this situation?

QuestionsCategory: PMPAs part of project execution, a contractor proposed and conducted site acceptance tests and pre-implementation technical training. However, during the implementation phase, the project manager notes a clear gap in the project team’s competence in following the implementation of the technical requirements. What should the project manager have done to avoid this situation?
Admin Staff asked 1 year ago
As part of project execution, a contractor proposed and conducted site acceptance tests and pre-implementation technical training. However, during the implementation phase, the project manager notes a clear gap in the project team's competence in following the implementation of the technical requirements.
What should the project manager have done to avoid this situation?

A. Ensured the training conducted by the contractor used standard methods

B. Reviewed the proposed training with the contractor

C. Performed a proper training needs assessment

D. Prepared proper training outcome measurements










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.