As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail. What should the project manager do first to decide how to manage this project? A. Select a predictive development life cycle based on the team's experience B. Determine the most appropriate life cycle approach for the project C. Register all requirements into a backlog for further detailed analysis D. Split the requirements, put them into two separate projects, and apply different approaches Correct Answer: C This question is in PMP exam For getting PMP Certificate