At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release. What should the project manager do? A. Ask the product owner to provide more details in the standup. B. Organize a workshop after the standup to assess the impact. C. Prepare a budget change request for additional resources. D. Create a new product backlog item for the next sprint planning. Correct Answer: B This question is in PMP exam For getting PMP Certificate