Before a daily standup, a team member informed the project manager that they have accepted a job offer at another company. The team member explains that they plan to present their resignation to the functional manager. What should the project manager do next? A. Contact the product owner and review the current sprint backlog. B. Communicate to the team members at the daily standup. C. Alert the functional manager about possible delivery delays. D. Contact the functional manager and develop a mitigation strategy. Correct Answer: D This question is in PMP exam For getting PMP Certificate