Due to price in ation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced. What is the first approach the project manager should take?

QuestionsCategory: PMPDue to price in ation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced. What is the first approach the project manager should take?
Admin Staff asked 1 year ago
Due to price in ation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced.
What is the first approach the project manager should take?

A. Ask the business stakeholders to reduce the number of features required for the product.

B. Delay the hiring of the additional resource until market conditions are favorable to work within project requirements.

C. Ask the functional managers to source a less experienced and less expensive team member for the project.

D. Request the current team to analyze the work planned for the additional resource.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.