During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project. Which action should the project manager take?

QuestionsCategory: PMPDuring a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project. Which action should the project manager take?
Admin Staff asked 1 year ago
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project.
Which action should the project manager take?

A. Facilitate a supportive level of engagement for this stakeholder.

B. Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C. Perform a qualitative risk analysis using a probability and impact matrix.

D. Ensure the key information is accurate and monitor the situation as the project progresses.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.