During a new system implementation, an IS auditor has been assigned to review risk management at each milestone. The auditor finds that several risks to project benefits have not been addressed. Who should be accountable for managing these risks? A. Project manager B. Information security officer C. Project sponsor D. Enterprise risk manager Suggested Answer: C Community Answer: C This question is in CISA Certified Information Systems Auditor Exam For getting Certified Information Systems Auditor (CISA) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. Trademarks, certification & product names are used for reference only and belong to ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams.