During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal impact on project resources. However, the client has only been focused on the next milestone. How should the project manager approach this situation? A. Apply additional resources to realize the early deliverable and ensure the next milestone is achieved. B. Focus on the deliverable of the next project milestone as per the client's strict instructions. C. Review the change management plan to discuss early benefits realization with the client. D. Evaluate whether the client's request will add extra features to the project deliverable. Correct Answer: C This question is in PMP exam For getting PMP Certificate