During a project’s initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion. What should the project manager do next?

QuestionsCategory: PMPDuring a project’s initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion. What should the project manager do next?
Admin Staff asked 1 year ago
During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?

A. Discuss this issue with the project sponsor to request additional funding to implement mitigation

B. Prequalify contractors with proven track records to eliminate productivity concerns

C. Add construction productivity to the risk register and develop a mitigation strategy for site execution

D. Hire a construction management consultant to develop a comprehensive site execution plan C










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.