During a project's third iteration, two of the existing team members were replaced. As the project entered the next iteration, the team velocity dropped and the performance started to slip. What should the project manager do? A. Guide the team to revert back to the forming and storming stages. B. Discuss the decrease in productivity with human resources (HR). C. Convene a team building event to address key performance indicators (KPIs). D. Escalate the issue to the project sponsor. Correct Answer: A This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer