During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog. What should the project manager do next?

QuestionsCategory: PMPDuring an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog. What should the project manager do next?
Admin Staff asked 1 year ago
During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog. What should the project manager do next?

A. Reevaluate the backlog priority with the product owner since the velocity has been impacted.

B. Reevaluate the scope of the current iteration to keep the same velocity and timeline.

C. Reevaluate the velocity as the iteration duration will be impacted by new requirements.

D. Reevaluate the project schedule as the velocity will be impacted by the loss of resources.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.