During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible. What approach should be used in this situation? A. The team facilitator gets support from external team members. B. The team members bring in a specialist to help them C. The product owner moves it to the product backlog. D. The cross-functional team member work together to complete the activity Correct Answer: D This question is in PMP exam For getting PMP Certificate