During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible. What approach should be used in this situation?

QuestionsCategory: PMPDuring an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible. What approach should be used in this situation?
Admin Staff asked 1 year ago
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.
What approach should be used in this situation?

A. The team facilitator gets support from external team members.

B. The team members bring in a specialist to help them

C. The product owner moves it to the product backlog.

D. The cross-functional team member work together to complete the activity










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.