During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project manager do?

QuestionsCategory: PMPDuring iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project manager do?
Admin Staff asked 1 year ago
During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.
What should the project manager do?

A. Cancel the current iteration and reschedule it with the dependent activity.

B. Include the dependent activity in the current iteration for team

C. Ensure team B prioritizes the dependent activity in iteration three.

D. Assign the two critical activities to team B in iteration two.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.