During project execution, a client asks to add one more features to the product. After performing a change request analysis, the project manager realizes the necessary equipment will not be available in time to support this new feature, resulting in the project team being idle. What should the project manager do next? A. Establish a contingency reserve. B. Rent ready-made equipment. C. Escalate the risk to senior management. D. Perform integrated change control. Correct Answer: D This question is in PMP exam For getting PMP Certificate