During project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?

QuestionsCategory: PMPDuring project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?
Admin Staff asked 10 months ago
During project implementation, one team finds out that a key project deliverable was not budgeted.
What should the project manager do first?

A. Escalate the issue to the project sponsor for resolution.

B. Hold the team accountable and ask for an immediate solution.

C. Meet with the team to discuss alternatives.

D. Remove the deliverable from the project scope.










Correct Answer: C