During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one? A. Warning signs B. Symptoms C. Risk rating D. Cost of the project Suggested Answer: D The cost of the project is not an indicator of risk urgency. The affect of the risk on the overall cost of the project may be considered, but it is not the best answer. Incorrect Answers: A: Warning signs are an indicator of the risk urgency. B: Symptoms are an indicator of the risk urgency. C: The risk rating can be an indicator of the risk urgency. This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.