During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays. What should the project manager have done to manage the issue?

QuestionsCategory: PMPDuring the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays. What should the project manager have done to manage the issue?
Admin Staff asked 1 year ago
During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted.
Several project stakeholders are now frustrated with the delays.
What should the project manager have done to manage the issue?

A. identified and reported the issue

B. Monitored and controlled the issue

C. identified the appropriate response and had it implemented

D. Communicated any identified action to impacted stakeholders










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.