During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays. What should the project manager have done to manage the issue? A. identified and reported the issue B. Monitored and controlled the issue C. identified the appropriate response and had it implemented D. Communicated any identified action to impacted stakeholders Correct Answer: C This question is in PMP exam For getting PMP Certificate