During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?

QuestionsCategory: PMPDuring the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?
Admin Staff asked 1 year ago
During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans.
What should the project manager do first?

A. Ask the neighbor to submit a formal complaint about their concerns.

B. Inform the neighbor that the complaint will be escalated to the project sponsor.

C. Inform the neighbor that all of the project documentation has been approved.

D. Ask the neighbor to leave the site immediately because the site is on private property.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.