During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line. How should the project manager address the situation?

QuestionsCategory: PMPDuring the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line. How should the project manager address the situation?
Admin Staff asked 1 year ago
During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?

A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule

B. Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project

C. Push out the project timeline according to the vacation plan in place based on the recent company policy

D. Discuss the vacation plan and include scheduling changes in the change log database










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.