During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a con icting operational schedule. What should the project manager do?

QuestionsCategory: PMPDuring the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a con icting operational schedule. What should the project manager do?
Admin Staff asked 1 year ago
During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a con icting operational schedule.
What should the project manager do?

A. Encourage the team member to prioritize scheduled project activities.

B. Replace the team member with another available resource on the team.

C. Discuss the situation with the team member's functional manager to see if the schedule can be adjusted.

D. Check with the project management office (PMO) on the available resources to complete the activities.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.