During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks. How should the project manager address this situation? A. Communicate the concerns to the project management office (PMO) during the weekly project reports B. Call for a team meeting to decide if the changes should be included C. Initiate the change request to modify the scope and adjust the timelines D. Conduct an impact analysis and present the results to the steering committee for approval D Correct Answer: D This question is in PMP exam For getting PMP Certificate