During the fourth sprint, a project manager noticed that none of the customer representatives have participated in any of the sprints. The team told the project manager that they had a prototype ready. What should the project manager do next?

QuestionsCategory: PMPDuring the fourth sprint, a project manager noticed that none of the customer representatives have participated in any of the sprints. The team told the project manager that they had a prototype ready. What should the project manager do next?
Admin Staff asked 1 year ago
During the fourth sprint, a project manager noticed that none of the customer representatives have participated in any of the sprints. The team told the project manager that they had a prototype ready.
What should the project manager do next?

A. Contact the customer to confirm that they received updates of the work in progress (WIP).

B. Tell the team to create a prototype manual to provide guidance for the end user.

C. Deliver a presentation about the capabilities to the quality assurance (QA) team.

D. Invite the customer representatives to the review meeting to review the prototype with the team.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.