During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting. What should the project manager do? A. Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome B. Update the communications management plan and implement the change C. Meet with the project sponsor to discuss how to address the situation D. Meet with the stakeholder prior to the meeting to obtain their opinion Correct Answer: D This question is in PMP exam For getting PMP Certificate