During the last iteration of a hybrid project., one of the key members of the team wants to leave the project. What should the project manager do to address this concern? A. Update the burndown chart to re ect this resource's absence. B. Keep activities as planned regardless of the resource change. C. Have a meeting with the resource to understand the issue. D. Request an additional resource to nish the project. Correct Answer: C This question is in PMP exam For getting PMP Certificate