During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first? A. Ask the product manager to include the final user tests in the quality management plan. B. Ask the quality manager to include the final user tests in the quality management plan. C. Let the product go to market and wait for customer feedback regarding quality. D. Submit a change request to analyze a new set of quality tests. Correct Answer: B This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer