During user acceptance testing, a project sponsor asks the project manager to add a couple of features. To meet the rm go-live date, the project team will need to work overtime. What should the project manager do? A. Submit an emergency change request and assign tasks to the team. B. Request approval for overtime and a bonus to deliver on time. C. Inform the sponsor that the project team cannot commit to more work. D. Consult with the project team and provide options to the sponsor. Correct Answer: D This question is in PMP exam For getting PMP Certificate