For no apparent reason, the time required to complete daily processing for a legacy application is approaching a risk threshold. Which of the following activities should be performed FIRST? A. Suspend processing to investigate the problem B. Conduct a root cause analysis C. Temporarily increase the risk threshold D. Initiate a feasibility study for a new application  Suggested Answer: B This question is in CRISC exam For getting Risk and Information Systems Control Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by ISACA. The website does not contain actual questions and answers from ISACA's Certification Exams. Trademarks, certification & product names are used for reference only and belong to ISACA.