In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums. What should the project manager do next?

QuestionsCategory: PMPIn an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums. What should the project manager do next?
Admin Staff asked 1 year ago
In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.
What should the project manager do next?

A. Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.

B. Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.

C. Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.

D. Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.