In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

QuestionsCategory: PMPIn an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?
Admin Staff asked 1 year ago
In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

A. 30/40

B. 30/70

C. 40/30

D. 40/70










Correct Answer: A

This question is in PMP exam