In an agile team, some of the team members are coming forward to ask for more autonomy on the project. What should the project manager do in this situation?

QuestionsCategory: PMPIn an agile team, some of the team members are coming forward to ask for more autonomy on the project. What should the project manager do in this situation?
Admin Staff asked 1 year ago
In an agile team, some of the team members are coming forward to ask for more autonomy on the project.
What should the project manager do in this situation?

A. Encourage the team lead to make decisions.

B. Encourage the team members to make decisions.

C. Discourage them as con icts may be created.

D. Discourage this request, as it is for the management team.










Correct Answer: B

This question is in PMP exam