In an ongoing project, the customer, who has been the main contact for the project, informs the project manager that they will be introducing a new contact person due to their busy schedule. Moving forward, the new contact will also be making key decisions. What should the project manager do next? A. Update the stakeholder register with the new contact's details. B. Inform the project team of the new point of contact. C. Update the communications management plan. D. Request a meeting with the customer and the new contact. Correct Answer: D This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer