Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments. How should the project manager impartially prioritize the requirements to be integrated? A. Retain only requirements that result in pro table revenue growth. B. Ensure the CEO selects the requirements from all department leaders. C. Give each department a fixed budget that will cover ten requirements. D. Rank the requirements with the highest benefit-cost ratio as more important. Correct Answer: D This question is in PMP exam For getting PMP Certificate