Midway through the execution of an agile protect there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next? A. Schedule a meeting with the team to assess the impact of the change B. Escalate to the product owner and cancel the upcoming iterations C. Prepare a user story to handle the change and assign it to the next iteration D. Update the risk-prioritized backlog with the strategic change Correct Answer: A This question is in PMP exam For getting PMP Certificate