One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager. What should the project manager do?

QuestionsCategory: PMPOne of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager. What should the project manager do?
Admin Staff asked 1 year ago
One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager.
What should the project manager do?

A. Review the integrated change control process with all the stakeholders.

B. Escalate the misalignment to the project management office (PMO) and the functional manager's director.

C. Ask the project management office (PMO) to recover the cost of xing it from the other team's budget.

D. Request dedicated business resources to support functional testing.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.