Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and responsibilities to work on CSI initiatives. (2) Measure and review that the CSI plan is executed and its objectives are being achieved. (3) Identify the scope, objectives and requirements for CSI. (4) Decision on implementation of further enhancement. A. 3-1-2-4 B. 3-4-2-1 C. 1-3-2-4 D. 2-3-4-1 Correct Answer: A This question is in ITIL Foundation exam For getting ITIL Foundation Certificate
Please login or Register to submit your answer