Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one?

QuestionsCategory: GISFPart of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one?
Admin Staff asked 6 months ago
Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one?

A. Configuration Status Accounting

B. Configuration Item Costing

C. Configuration Identification

D. Configuration Verification and Auditing








 

Suggested Answer: B



This question is in GISF exam 
For getting GIAC Information Security Fundamentals (GISF) Certificate

Disclaimers:
The website is not related to, affiliated with, endorsed or authorized by GIAC.
Trademarks, certification & product names are used for reference only and belong to GIAC.

Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.