Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one? A. Configuration Status Accounting B. Configuration Item Costing C. Configuration Identification D. Configuration Verification and Auditing  Suggested Answer: B This question is in GISF exam For getting GIAC Information Security Fundamentals (GISF) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by GIAC. Trademarks, certification & product names are used for reference only and belong to GIAC.
Please login or Register to submit your answer