Refer to the exhibit. An engineer extends a Cisco ACI Multi-Pod setup to a Cisco ACI Multi-Site implementation. Which action allows the interconnection? A. Configure BIDIR-PIM in the IPN and ISN B. Use dedicated uplinks on Site 1 spines for ISN connections C. Connect all spines to the IPN and ISN D. Filter the advertisement of the Site 2 TEP pool into the IPN Â Suggested Answer: A This question is in 300-630 Implementing Cisco Application Centric Infrastructure - Advanced (DCACIA) Exam For getting Cisco Certified Network Professional Data Center (CCNP Data Center) Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by Cisco. Trademarks, certification & product names are used for reference only and belong to Cisco. The website does not contain actual questions and answers from Cisco's Certification Exam.
Please login or Register to submit your answer